ServiceNow Certified Implementation Specialist – Strategic Portfolio Management — Question 18
What is a resource event?
Answer options
- A. A non-scheduled activity impacting capacity.
- B. A block of time that a resource spends on a task.
- C. An external event.
- D. An event scheduled by a project manager.
Correct answer: B
Explanation
The correct answer is B because a resource event specifically refers to the time a resource is dedicated to a task. Option A describes an unscheduled impact, which does not define a resource event. Option C refers to an external occurrence, while D indicates a planned event, but not specifically related to resource allocation.