ServiceNow Certified Implementation Specialist – Strategic Portfolio Management — Question 13
Which property controls the changes in cost and resource plans with respect to the change in the start date of a demand or project?
Answer options
- A. ‘Change Resource Plan, Cost Plan and Benefit Plan Start Date with Demand or Project Start Date Change’.
- B. ‘Enable altering of planned date for task in WIP/Closed’.
- C. ‘Rollup project start date from tasks’.
- D. ‘Calculate ROI percentage based on a project's estimated cost and its net value’.
Correct answer: A
Explanation
The correct answer, A, specifies that it directly addresses the synchronization of resource and cost plans with the demand or project start date changes. Options B, C, and D do not relate to managing changes in resource and cost plans based on start date adjustments, making them irrelevant in this context.