ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 83
A program is a container for the following except for:
Answer options
- A. Program tasks
- B. Issues
- C. Cost plans
- D. Portfolios
Correct answer: D
Explanation
The correct answer is D because portfolios are a higher-level grouping of programs and projects, not a component of a program itself. Options A, B, and C are all elements that can be found within a program's structure.