ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 82
What happens to resource allocations with actual hours after a resource plan is cancelled?
Answer options
- A. The allocated hours remain until the project is closed.
- B. The allocated hours become zero and the actual hours are retained.
- C. A resource plan with actual hours cannot be canceled.
- D. They are automatically moved to the next resource plan in the project.
Correct answer: B
Explanation
The correct answer is B because when a resource plan is canceled, the allocated hours are reset to zero, but any actual hours worked are preserved for record-keeping. Option A is incorrect as the allocated hours do not remain; option C is false because resource plans can be canceled; and option D is misleading since the hours are not transferred to a new plan.