ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 70
Using the Request type field on a resource plan, which options can be used to request a resource? (Choose three.)
Answer options
- A. Month
- B. Hours
- C. FTE
- D. Person Days
- E. Day
Correct answer: B, C, D
Explanation
The correct answers, B (Hours), C (FTE), and D (Person Days), are all valid units for requesting resources, allowing for flexibility in how resources are allocated. Options A (Month) and E (Day) do not fit within the standard request types for resource planning, as they do not directly represent a request for resource allocation in the same context.