ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 69

If an it_project_manager does not want to equally distribute hours across the resource plan time frame, what allocation spread should be used?

Answer options

Correct answer: A

Explanation

The correct answer is A, Front Load, which means allocating more resources at the beginning of the project. This approach is beneficial for projects with early milestones. The other options either suggest an even distribution or a late allocation, which do not align with the requirement to avoid equal distribution.