ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 65
Can an it_project_manager convert a task to a milestone?
Answer options
- A. Yes, it must be manually done from the project record.
- B. Yes, from the planning console right-click a task and select convert to milestone.
- C. No, the task must be deleted and re-created.
- D. No, this can only be done by an admin.
Correct answer: B
Explanation
The correct answer is B because the planning console allows users to easily convert tasks to milestones with a simple right-click action. Option A is incorrect as it does not provide the straightforward method available in the planning console. Options C and D are also incorrect because they unnecessarily complicate the process and suggest limitations that do not exist for project managers.