ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 64

How is the Resource Management application activated?

Answer options

Correct answer: A

Explanation

The correct answer is A, as the Resource Management application is specifically activated through the PPM Standard plugin installation. The other options do not apply because the Resource Management application does not come with the Release Management plugin, is not linked to user addition, and does not install automatically with the system.