ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 149
What is the formula for Forecasted Utilization?
Answer options
- A. Allocated Hours/Capacity
- B. (Allocated Hours + Confirmed Hours)/Capacity
- C. Confirmed Hours/Capacity
- D. Assigned Hours/Capacity
Correct answer: B
Explanation
The correct answer is B because Forecasted Utilization is determined by summing Allocated and Confirmed Hours and then dividing by Capacity. Options A, C, and D do not account for both Allocated and Confirmed Hours, thus they do not provide an accurate calculation of Forecasted Utilization.