ServiceNow Certified Implementation Specialist – Project Portfolio Management — Question 148
When a demand is converted to a project, the following fields retain the start and due date (Choose two.)
Answer options
- A. Approved start date
- B. Actual start date
- C. Approved end date
- D. Actual end date
Correct answer: C, D
Explanation
The correct answers are C and D because the Approved end date and Actual end date are the fields that maintain the timelines when transforming a demand into a project. The Approved start date and Actual start date do not retain the original start and due dates during this conversion.