In the baseline Change - Normal model, when the Change request goes to the Review state, what happens to the implementation and testing tasks, if they have not been closed.

Answer options

Correct answer: A

Explanation

The correct answer is A, as in the baseline Change - Normal model, tasks that remain open are automatically canceled when the Change request enters the Review state. Options B and C are incorrect because tasks are not closed or assigned; they are canceled. Option D is also wrong because no error is generated; the tasks are simply canceled.