ServiceNow Certified Implementation Specialist – Field Service Management — Question 34

When defining a maintenance schedule, what type of trigger would you use for work to be performed based on time and count?

Answer options

Correct answer: B

Explanation

The correct answer is B, as 'Duration or Meter' triggers are specifically designed for scheduling maintenance based on elapsed time or usage counts. The other options either combine unrelated triggers or omit one of the necessary components, making them unsuitable for this scenario.