ServiceNow Certified Implementation Specialist – Field Service Management — Question 34
When defining a maintenance schedule, what type of trigger would you use for work to be performed based on time and count?
Answer options
- A. Meter and Script
- B. Duration or Meter
- C. Script and Duration
- D. Duration or Script
Correct answer: B
Explanation
The correct answer is B, as 'Duration or Meter' triggers are specifically designed for scheduling maintenance based on elapsed time or usage counts. The other options either combine unrelated triggers or omit one of the necessary components, making them unsuitable for this scenario.