Professional Scrum Product Owner I (PSPO I) — Question 22
When must the Product Owner participate in the Daily Scrum? (Choose the best answer.)
Answer options
- A. When there are impediments to discuss.
- B. When the Product Owner is actively working on items on the Sprint Backlog; however, they participate as a Developer.
- C. When the Scrum Master asks the Product Owner to attend.
- D. When the Product Owner needs to represent the stakeholders' point of view to the Developers.
Correct answer: B
Explanation
The correct answer is B because the Product Owner can participate in the Daily Scrum when they are directly involved in Sprint Backlog items, but they should adopt the role of a Developer in this scenario. Other options either misinterpret the role of the Product Owner or suggest attendance under conditions that don't align with Scrum principles.