Professional Scrum Product Owner I (PSPO I) — Question 21
Scrum requires that the Product Owner must use which of the following items? (Choose all that apply.)
Answer options
- A. Burndown chart.
- B. Feature bum-up.
- C. Critical Path Analysis.
- D. Project Gantt chart.
- E. None of the above.
Correct answer: E
Explanation
The correct answer is E because Scrum does not mandate the use of specific tools like a Burndown chart, Feature bum-up, Critical Path Analysis, or a Project Gantt chart for the Product Owner. These items may be useful in various contexts but are not required in the Scrum framework.