True or False: Product Owners must specify complete acceptance criteria for a Product Backlog item before the Developers can select the item in Sprint Planning.
Answer options
- A. True
- B. False
Correct answer: B
Explanation
The correct answer is False because while having acceptance criteria is beneficial, it is not mandatory for a Product Owner to have complete acceptance criteria defined before Developers can select a backlog item. Developers can choose items based on their understanding and collaboration with the Product Owner.