Professional Scrum Product Owner I (PSPO I) — Question 18
When the Developers determine that they will not be able to finish the complete forecast, who has to be present when reviewing and adjusting the Sprint work selected? (Choose the best answer.)
Answer options
- A. The Product Owner and all stakeholders.
- B. The Scrum Master and the Developers.
- C. The Scrum Master, project manager and the Developers.
- D. The Product Owner and the Developers.
Correct answer: D
Explanation
The correct answer is D because the Product Owner and the Developers must collaborate to reassess the Sprint work based on the current situation. Options A, B, and C include roles or individuals who are not required for this specific interaction, making them less relevant in this context.