Professional Scrum Master II (PSM II) — Question 75

The director of engineering in your organization always stresses the importance of meeting deadlines in order for the engineering department to be seen as a reliable source for the product management department. The director has calculated that the team's velocity needs to increase an additional 15% to meet the commitment he made to management for the release date of the product.
He asks Steven, the team's Scrum Master, to increase his team's velocity. Which would be the best two responses for Steven to take? (Choose two.)

Answer options

Correct answer: A, B

Explanation

Option A is correct as it emphasizes the proper use of velocity for forecasting rather than making predictions, while directing the director to the Product Owner for updates. Option B is also correct since addressing organizational impediments and collaborating on solutions is essential for improving productivity. The other options either misinterpret Scrum principles or place responsibilities outside of the Scrum Master's role.