Professional Scrum Master II (PSM II) — Question 73

Your organization requires all Increments to pass user acceptance testing (UAT) before it is allowed to be released to production.
Is it a good idea to postpone UAT until the end of the project to prevent the Development Team from being disrupted during the Sprints?

Answer options

Correct answer: A

Explanation

The correct answer is A because delaying UAT would hinder transparency regarding the Product Increment's state and extend the feedback loop, making it harder to address issues promptly. Options C and D suggest that disruption is acceptable, which undermines the iterative feedback process essential for Agile development. Option B is too vague and does not directly address the implications of postponing UAT.