Professional Scrum Master II (PSM II) — Question 42

Steven, the Scrum Master, observes that one of the Development Team members is not attending the Daily Scrum. The Development Team feels this is ok as they all sit in the same area and already have constant communication throughout the day.
Which is the best action for Steven to take?

Answer options

Correct answer: C

Explanation

The correct answer is C because it encourages the Development Team to reflect on the importance and potential risks associated with attendance at the Daily Scrum. Options A and B impose mandates rather than fostering team ownership, while D incorrectly suggests that the Scrum Master has no role in facilitating the team’s process.