Professional Scrum Master II (PSM II) — Question 26
A Scrum Team has been working on a product for several iterations and has an average velocity of 55 units of 'done' work per Sprint. A second team will be added to work on the same product.
What might be the impact on the original team?
Answer options
- A. Their velocity is likely not affected and will remain at 55.
- B. Their velocity is likely to drop and be less than 55.
- C. Their velocity is likely to rise and be more than 55.
Correct answer: B
Explanation
The introduction of a second team can lead to increased coordination and communication challenges, which may disrupt the original team's workflow and reduce their efficiency. As a result, their velocity is likely to drop and fall below the current average of 55 units. Options A and C do not consider the potential negative impact of adding another team on the original team's productivity.