Professional Scrum Master II (PSM II) — Question 25

Steven is a Scrum Master that was hired to help an organization, that is new to Scrum, understands and enacts Scrum effectively.
Which three activities would be acceptable? (Choose three.)

Answer options

Correct answer: B, C, E

Explanation

The correct answers are B, C, and E because they focus on providing support and education to the team and stakeholders, which is essential for a successful Scrum implementation. Options A and D are inappropriate as they impose strict requirements and penalties, which can create a negative environment. Option F is not a standard practice in Scrum and may detract from the primary purpose of Retrospectives.