Professional Scrum Master II (PSM II) — Question 171

During the implementation of an item in the Sprint Backlog, a conflict arises between team members about what work is needed to make the item 'done'. Some say it is a part of the Definition of Done and others say it isn't. Steven, the Scrum Master, observes a debate forming and members beginning to take sides.
What is the best action for Steven to take?

Answer options

Correct answer: C

Explanation

The correct answer, C, is ideal because it promotes collaboration and empowers the team to address their conflicts constructively, enhancing their effectiveness. A focuses too much on interpretation without team input, B suppresses the dialogue which can lead to unresolved issues, and D incorrectly delegates responsibility to the Product Owner instead of fostering team ownership and resolution.