Professional Scrum Master II (PSM II) — Question 170

At the end of the eighth Sprint, the internal sponsors are upset and angry with the progress of the product being built. The current state of the product is not as expected and will require additional Sprints and more budget than originally anticipated at the start of the project.
What factors may have led to this? (Choose three.)

Answer options

Correct answer: A, B, E

Explanation

The correct answers, A, B, and E, highlight the lack of engagement and communication between the Product Owner and sponsors, as well as the Scrum Master's failure to ensure transparency. Options C and D, while relevant, do not directly address the sponsors' dissatisfaction as effectively as the correct choices, which focus on engagement and oversight issues.