Professional Scrum Master II (PSM II) — Question 141
A key measure of success for the Product Owner is velocity.
Answer options
- A. True
- B. False
Correct answer: B
Explanation
The correct answer is B because velocity is primarily a measure for the development team to gauge how much work they can complete in a sprint, rather than a direct measure of the Product Owner's success. The Product Owner's effectiveness is more about managing the product backlog and ensuring stakeholder satisfaction than about velocity metrics.