Professional Scrum Master II (PSM II) — Question 126
How often should Development Team membership change?
Answer options
- A. Frequently in order to share knowledge.
- B. As needed, while taking into account a short term reduction in productivity.
- C. Never, as it conflicts with the Scrum process.
- D. As needed, as long as it doesn't impact productivity.
Correct answer: B
Explanation
The correct answer is B because changes in the Development Team should be made when necessary, but it's important to recognize that this may lead to a short-term decrease in productivity. Options A and D suggest more frequent or unrestricted changes, which could disrupt team dynamics. Option C is incorrect as it misinterprets Scrum's flexibility regarding team composition.