Professional Scrum Master II (PSM II) — Question 125
The Development Team should have all the skills and competencies needed to:
Answer options
- A. Turn the Product Backlog items it selects into a potentially releasable product increment of functionality.
- B. Do all of the development work in order to handoff to the testers in the subsequent Sprint.
- C. Complete the project within the estimate as committed to the Product Owner.
Correct answer: A
Explanation
The correct answer is A because the Development Team must be capable of delivering potentially releasable increments of functionality from the Product Backlog. Option B is incorrect as it suggests a handoff to testers, which contradicts the collaborative nature of Scrum. Option C is not correct because the focus is not solely on completing the project within an estimate but on delivering value incrementally.