Professional Scrum Master II (PSM II) — Question 123
What should the Development Team do if they are approached by someone outside the team and asked to add a `very important` item to a Sprint that is in progress?
Answer options
- A. Add the item to the bottom of the Sprint Backlog.
- B. Replace an item in the current Sprint of equal size.
- C. Add the item to the top of the next Sprint Backlog.
- D. Inform the Product Owner so he/she can work with the person.
Correct answer: D
Explanation
The correct answer is D because the Development Team should inform the Product Owner, who is responsible for managing the Product Backlog and prioritizing items. Adding items directly to the Sprint Backlog, as suggested in A or B, disrupts the Sprint's focus and commitment. Option C is also incorrect because it suggests modifying the next Sprint without proper evaluation by the Product Owner.