Professional Scrum Master II (PSM II) — Question 123

What should the Development Team do if they are approached by someone outside the team and asked to add a `very important` item to a Sprint that is in progress?

Answer options

Correct answer: D

Explanation

The correct answer is D because the Development Team should inform the Product Owner, who is responsible for managing the Product Backlog and prioritizing items. Adding items directly to the Sprint Backlog, as suggested in A or B, disrupts the Sprint's focus and commitment. Option C is also incorrect because it suggests modifying the next Sprint without proper evaluation by the Product Owner.