Professional Scrum Master II (PSM II) — Question 122
Who manages the progress of work during a Sprint?
Answer options
- A. The Scrum Master
- B. The Product Owner
- C. The Team Lead
- D. The Development Team
Correct answer: D
Explanation
The Development Team is responsible for managing their own work progress during a Sprint, ensuring they meet the Sprint goals. The Scrum Master facilitates the process and removes obstacles, while the Product Owner focuses on defining the product backlog. The Team Lead role is not a specific Scrum role and may vary in function.