Professional Scrum Master II (PSM II) — Question 11

What are typical Product Owner activities during Sprint 0?

Answer options

Correct answer: E

Explanation

The correct answer is E because Sprint 0 is not recognized in the Scrum framework; thus, there are no activities associated with it. Options A, B, C, and D imply a structured approach that does not align with the principles of Scrum, where the focus is on iterative development rather than project planning before the initial Sprint.