What are typical Product Owner activities during Sprint 0?
Answer options
- A. Creating a project plan based on the defined timeline.
- B. Ensuring there is enough work to do for at least three Sprints.
- C. Creating User Stories based on the requirements document.
- D. Allocating enough resources before starting Sprint 1.
- E. There is no such thing as Sprint.
Correct answer: E
Explanation
The correct answer is E because Sprint 0 is not recognized in the Scrum framework; thus, there are no activities associated with it. Options A, B, C, and D imply a structured approach that does not align with the principles of Scrum, where the focus is on iterative development rather than project planning before the initial Sprint.