Professional Scrum Master II (PSM II) — Question 10
What should a Development Team do if it realizes it has selected too much work after starting the Sprint?
Answer options
- A. Modify the definition of ג€Doneג€ to ensure all Product Backlog items can be done by the end of the Sprint.
- B. Work with the Product Owner to remove some work or Product Backlog items as soon as possible.
- C. Add additional team members to handle the extra work.
- D. Continue working and update the Product Owner at the Sprint Review.
Correct answer: B
Explanation
The correct answer is B because the Development Team should immediately collaborate with the Product Owner to adjust the scope of work to ensure focus and deliverability within the Sprint. Option A is incorrect as modifying the definition of 'Done' does not address the issue of overcommitment. Option C is not advisable as adding team members mid-Sprint may not be practical or effective. Option D fails to provide a proactive solution, as it delays addressing the issue until the Sprint Review.