Professional Scrum Master I (PSM I) — Question 88
What is the purpose of a Sprint Review?
Answer options
- A. To take time to judge the validity of the project.
- B. To inspect the product Increment with the stakeholders and collect feedback on next steps.
- C. To review the Scrum Team's activities and processes during the Sprint.
- D. To build team sprint.
Correct answer: B
Explanation
The correct answer, B, highlights the key role of the Sprint Review in engaging stakeholders to evaluate the product Increment and obtain valuable feedback for future improvements. Option A misinterprets the purpose by focusing on project validity, while option C centers on team processes rather than the product. Option D is irrelevant as it does not address the Sprint Review's primary goal.