Professional Scrum Master I (PSM I) — Question 87
Who can cancel a Sprint?
Answer options
- A. The Scrum Team.
- B. The Scrum Master.
- C. The Product Owner.
- D. The Stakeholders.
Correct answer: C
Explanation
The correct answer is C, as the Product Owner is the only role with the authority to cancel a Sprint when the Sprint Goal is no longer viable. The Scrum Team, Scrum Master, and Stakeholders do not have the formal power to cancel a Sprint.