Professional Scrum Master I (PSM I) — Question 4

Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the Development Team estimated as 90% done. The
Development Teams, feeling the need to meet the plan, figured that a velocity of 17 was within their reach.
A good way to continue is:

Answer options

Correct answer: D

Explanation

The correct answer is D because it emphasizes the importance of ensuring that adequate resources and time are allocated for the remaining work, which is crucial for a successful product release. Option A, while focusing on making work 'Done', does not address the need for additional funding or time. Option B suggests increasing team size, which isn't a guaranteed solution for meeting deadlines. Option C points out failures in Scrum practices but does not provide a constructive path forward.