Professional Scrum Master I (PSM I) — Question 3

A properly functioning Scrum Team will have at least one Release Sprint and may well have several.

Answer options

Correct answer: B

Explanation

The correct answer is B because a Scrum Team is not required to have a Release Sprint; they may have multiple Sprints focused on product increments without specifically designating a Release Sprint. Therefore, it is possible for a Scrum Team to function effectively without any Release Sprints.