Professional Scrum Master I (PSM I) — Question 27

A Scrum Team has been working on a product for nine Sprints. A new Product Owner comes in, understanding he is accountable for the Product Backlog.
However, he is unsure about his responsibilities. Which two activities are part of the Product Owner role according to Scrum? (Choose two.)

Answer options

Correct answer: A, B

Explanation

The correct answer is A and B because a key responsibility of the Product Owner is to ensure that the most valuable functionality is prioritized and to engage with stakeholders for feedback and alignment. Options C, D, and E do not align with the Product Owner's role, as they focus more on detailed specifications and testing, which are not primary responsibilities.