Professional Scrum Master I (PSM I) — Question 26
For which is the Scrum Master responsible?
Answer options
- A. Managing the performance of the Scrum Team.
- B. The meetings and the objectives that a Scrum Team sets for itself.
- C. The Scrum framework being adopted and used properly.
- D. Keeping track of resource allocation.
Correct answer: C
Explanation
The Scrum Master is primarily responsible for ensuring that the Scrum framework is being properly implemented and utilized by the team, which makes option C the correct answer. Options A and D are responsibilities that fall outside the Scrum Master's role, as they focus on team performance and resource management respectively. Option B relates to the Scrum Team's self-management, which is also not the Scrum Master's primary responsibility.