Professional Scrum Master I (PSM I) — Question 174

When does a Sprint conclude? (Choose the best answer.)

Answer options

Correct answer: B

Explanation

The correct answer is B because a Sprint officially concludes after the Sprint Retrospective is held, which is a key event in the Scrum framework. While the other options mention important aspects of the Sprint, they do not define the formal end of the Sprint as clearly as the completion of the Retrospective.