Professional Scrum Master I (PSM I) — Question 174
When does a Sprint conclude? (Choose the best answer.)
Answer options
- A. When all Product Backlog items meet their Definition of Done.
- B. When the Sprint Retrospective is complete.
- C. When the Product Owner decides enough has been delivered to meet the Sprint Goal.
- D. When all the tasks are completed by the Developers.
Correct answer: B
Explanation
The correct answer is B because a Sprint officially concludes after the Sprint Retrospective is held, which is a key event in the Scrum framework. While the other options mention important aspects of the Sprint, they do not define the formal end of the Sprint as clearly as the completion of the Retrospective.