Professional Scrum Master I (PSM I) — Question 173
When is a Sprint over?
Answer options
- A. When the Product Owner says it is done.
- B. When all Product Backlog items meet their definition of ג€Doneג€.
- C. When all the tasks are completed.
- D. When the time-box expires.
Correct answer: D
Explanation
The correct answer is D because a Sprint officially ends when the time-box set for it runs out, regardless of the completion status of tasks or backlog items. Options A, B, and C suggest conditions that are not aligned with the Scrum framework's definition of a Sprint's conclusion.