Professional Scrum Master I (PSM I) — Question 173

When is a Sprint over?

Answer options

Correct answer: D

Explanation

The correct answer is D because a Sprint officially ends when the time-box set for it runs out, regardless of the completion status of tasks or backlog items. Options A, B, and C suggest conditions that are not aligned with the Scrum framework's definition of a Sprint's conclusion.