Professional Scrum Master I (PSM I) — Question 169
Who determines how work is performed during the Sprint?
Answer options
- A. The Developers
- B. The Scrum Team.
- C. The Scrum Master.
- D. Team manager.
- E. Subject matter experts.
Correct answer: A
Explanation
The Developers are responsible for determining how to achieve the goals set for the Sprint, which includes deciding on the processes and techniques to use. The Scrum Team encompasses all roles, but it is specifically the Developers who handle the execution of the work. The Scrum Master facilitates the process and ensures the team adheres to Scrum practices, while the Team manager and Subject matter experts do not directly influence how the Developers perform their work.