Professional Scrum Master I (PSM I) — Question 168

Which topics should be discussed in the Sprint Review?

Answer options

Correct answer: C

Explanation

The correct answer is C because the Sprint Review focuses on the product Increment and its progress. While the Scrum process and engineering practices may be relevant, they are not the primary focus of the review, making A and B less critical than discussing the product Increment. D is incorrect as it implies that all options are equally relevant to the Sprint Review.