Professional Scrum Master I (PSM I) — Question 155

Who is responsible for the sizing of Product Backlog items?

Answer options

Correct answer: A

Explanation

The correct answer is A, as it is the Developers who assess and size the Product Backlog items after discussing the requirements with the Product Owner to ensure clarity. Option B incorrectly suggests that the Product Owner has primary responsibility, while C implies that Developers work in isolation. D misplaces responsibility with senior personnel, and E mistakenly assigns the Scrum Master a role that does not involve sizing backlog items.