Professional Scrum Master I (PSM I) — Question 154
When is implementation of a Product Backlog item considered complete?
Answer options
- A. At the end of the Sprint.
- B. When the item has no work remaining in order to be potentially released.
- C. When Quality Assurance reports that the item passes all acceptance criteria.
- D. When all work in the Sprint Backlog related to the item is finished.
Correct answer: B
Explanation
The correct answer, B, indicates that a Product Backlog item is considered complete when it is ready for potential release, meaning all necessary work has been done. Option A is incorrect because completion is not solely determined by the end of the Sprint. Option C focuses on Quality Assurance, which is only part of the process, and option D is misleading as it doesn't emphasize the readiness for release.