Professional Scrum Master I (PSM I) — Question 154

When is implementation of a Product Backlog item considered complete?

Answer options

Correct answer: B

Explanation

The correct answer, B, indicates that a Product Backlog item is considered complete when it is ready for potential release, meaning all necessary work has been done. Option A is incorrect because completion is not solely determined by the end of the Sprint. Option C focuses on Quality Assurance, which is only part of the process, and option D is misleading as it doesn't emphasize the readiness for release.