Professional Scrum Master I (PSM I) — Question 138
Which are NOT appropriate topics for discussion in a Sprint Retrospective? (Choose two.)
Answer options
- A. Definition of ג€Doneג€.
- B. How the team does its work.
- C. Team relations.
- D. The value of work currently represented in the Product Backlog.
- E. Arranging the Sprint Backlog for the next Sprint.
Correct answer: D, E
Explanation
Options D and E are not suitable for discussion in a Sprint Retrospective because the focus should be on improving team processes and interactions, rather than on the specifics of the Product Backlog or planning for the next Sprint. Options A, B, and C are relevant as they pertain to the team's practices and dynamics.