Professional Scrum Master I (PSM I) — Question 137

Which of the following are true about the Product Owner role? (Choose two.)

Answer options

Correct answer: A, B

Explanation

The correct answers are A and B because the Product Owner is indeed a single individual responsible for managing and prioritizing the Product Backlog. Options C and D are incorrect as the Scrum framework specifies that the Product Owner role should be filled by one person, not shared or performed by a committee.