Professional Scrum Master I (PSM I) — Question 133
Which of the following are topics for the Developers to discuss at the Daily Scrum as they inspect their progress toward the Sprint Goal? (Choose three.)
Answer options
- A. What have we learned since yesterday, and how should we modify our plan to increase our ability to meet the Sprint Goal?
- B. Are there any impediments blocking progress toward the Sprint Goal?
- C. What will I be working on tomorrow?
- D. Why were you late?
- E. How many hours did I spend on the project yesterday?
- F. Are there any decisions that need to be made to maintain progress toward the Sprint Goal?
- G. Will today's work negatively impact our ability to meet the Sprint Goal for the Sprint following this one?
Correct answer: A, B, F
Explanation
The correct answers A, B, and F focus on assessing progress and addressing any obstacles or necessary decisions to meet the Sprint Goal. Options C, D, and E are more individual-focused and do not contribute to the team’s collective progress assessment, while G speculates on future impacts rather than addressing current progress.