Professional Scrum Master I (PSM I) — Question 132
The Sprint Backlog is a result of Sprint Planning, and it includes the Sprint Goal.
Answer options
- A. True
- B. False
Correct answer: A
Explanation
The statement is accurate because the Sprint Backlog is indeed created during the Sprint Planning meeting and it encompasses the Sprint Goal. Option B is incorrect as it contradicts the established principles of Scrum.