Professional Scrum Master I (PSM I) — Question 125
When might a Sprint be cancelled?
Answer options
- A. When the Developers determine the product plan is infeasible.
- B. When the Sprint Goal becomes obsolete.
- C. When the sales department has an important new opportunity.
- D. When it becomes clear that not everything will be finished by the end of the Sprint.
Correct answer: B
Explanation
The correct answer is B because a Sprint should be cancelled when the Sprint Goal is no longer relevant to the project's objectives. Options A, C, and D may indicate challenges or opportunities but do not directly necessitate cancelling the Sprint.