Professional Scrum Master I (PSM I) — Question 124
True or False: The Product Owner makes sure the Developers select enough from the Product Backlog for a Sprint to satisfy the stakeholders.
Answer options
- A. True
- B. False
Correct answer: B
Explanation
The correct answer is False because the responsibility of selecting the items from the Product Backlog lies with the Developers, not the Product Owner. The Product Owner prioritizes the backlog items, but it is up to the Developers to determine how much they can commit to within a Sprint.