Professional Scrum Master I (PSM I) — Question 124

True or False: The Product Owner makes sure the Developers select enough from the Product Backlog for a Sprint to satisfy the stakeholders.

Answer options

Correct answer: B

Explanation

The correct answer is False because the responsibility of selecting the items from the Product Backlog lies with the Developers, not the Product Owner. The Product Owner prioritizes the backlog items, but it is up to the Developers to determine how much they can commit to within a Sprint.