Professional Scrum Master I (PSM I) — Question 122

As the Development Team starts work during the Sprint, it realizes it has selected too much work to finish in the Sprint. What should it do?

Answer options

Correct answer: C

Explanation

The correct answer is C because the Development Team should address the issue early in the Sprint by discussing with the Product Owner to adjust the backlog. Option A is too late in the process, while B is not feasible as it disrupts team cohesion. Option D compromises the quality of work by altering the definition of 'Done'.