Professional Scrum Master I (PSM I) — Question 121

During a Sprint Retrospective, the Development Team proposes moving the Daily Scrum to only occur on Tuesdays and Thursdays. Which two are the most appropriate responses for the Scrum Master? (Choose two.)

Answer options

Correct answer: B, D

Explanation

Option B is correct because the Scrum Master should emphasize the importance of the Daily Scrum for planning updates. Option D is also correct as it involves understanding the Development Team's motivations and working together to enhance the effectiveness of the Daily Scrum. Options A, C, and E do not align with the Scrum Master's role in facilitating the team's understanding and improvement of their processes.